Prelude to the preparation of the washing machine

Jul 05, 2021

a. Check whether there is air leakage in the pipeline system, and if this happens, the maintenance personnel should be notified to repair.
b. Check whether the cleaning liquid is sufficient, if it is not enough, increase the cleaning liquid in time.
c. First jog the test run, and then run empty for 2-3 minutes, check whether the movement of the transmission system (motor, coupling, reducer) and the transport belt is stable, and confirm that everything is normal before production.
d. Open the oil slick elimination device (except without the oil slick elimination device) to start the oil slick elimination, so when the water pump is still on, the water surface is calm, the oil discharge effect is the best, stop the oil removal after the oil slick is basically eliminated, and the oil discharge is carried out by using the lunch break.